Sailboat Petrochemical Co.,Ltd. MTO Catalyst Dust Extration Project
Lanke Provides tanks top dust extration system for the 900,000 MT/YR DMTO unit in phase I of alcohol Quito cogeneration project in Sailboat Petrochemical Co., Ltd. Located in Lianyungang of Jiangsu Province, which includes tanks top dedusting of the fresh catalyst, the regerated catalyst and the spent catalyst. With SEI as the general contractor, the afford scope of Lanke included equipment, instruments, control systems, pipes and pipe fittings, installation, training and guidance of stat-off and debugging, and the dust extration will be put into operation in August 15th, 2015.